4D模型用于提高一个Za'abeel项目的生产力

伊德拉迪拜的“一个Za'abeel”,Mega混合使用项目,使用了4D模拟解决方案,用于采用Clash检测和增强的情景规划,用于安装世界上最大的悬臂。

伊特拉迪拜,'一个za'abeel'只是不是另一个摩天大楼,但无可否认的预计是迪拜天际线的标志性地标,在新的工程和设计标准中设置。该地标声称“重塑酋长国的天际线”与设计,该设计将与城市建造同义词。

该项目

一个Za'abeel项目的建设是巨大的(10亿美元)和复杂的。It includes two monumental towers (Tower A and Tower B) standing at 300 and 235 meters above the ground level, in between of which it has to be ‘linked’ via the world’s largest cantilever – a 228-meter-long panoramic sky concourse providing a 360-degree view of Dubai. The cantilever is a 9,000-ton structure and will weigh about 13,000 tons once it is assembled and the interiors are completed. Foreseen to be an iconic landmark, the building is expected to attract huge number of visitors as it will include a mall, a luxury hotel and multiple leisure activity zones. The construction of the project began in 2017, in presently under construction and the place is estimated to open in Winter 2021.

这个过程

一个Za'abeel项目是尖端设计和技术进步的组合。2017年,该项目的项目承包商,Alec Engineering.,使用无人机,BIM,3D和4D建模,以确保数十种利益相关者,包括建筑师,工程师和承包商,可以同时协作,协调和沟通并领导施工计划。在项目的初始阶段,使用无人机来调查项目现场,以捕获空间数据,并在将来补充建模过程中。额外的地理空间工具用于捕获图像(LIDAR,AERIAL IMIGERY)并建立不同的场景以了解项目的风险和建筑环境。

承包商还在构建阶段的每个方面使用3D建模,包括钢框架,机械系统和混凝土等施工的关键元件。4D BIM是“时间”维度,允许工程师计划和进行预测分析,以预测潜在的问题,并在以实际的现场建设开始之前跟踪和监控所有流程。从无人机收集的成像用于比较建模过程中创建的数字仿真,以确保将项目及时交付。使用4D建模,特别是Bentley的同步技术在这种巨大规模和复杂性的项目中,帮助利益相关者以完整的项目尽可能地显示为颗粒状和细节的图片,并在施工开始之前进行任何替代设计变化。使用Synchro,架构师和工程师可以测试所有可能的方案以获得“最佳结构”方案。

价值主张

该技术特别有助于冲突检测。一个特定的例子是当利益攸关方可以及时识别塔A的起重机的冲突与钢桥的计划,导致成本和时间效率。如果4D模型没有按时检测到潜在的冲突,则碰撞可能会延迟钢结构的结构。施工环境的4D型号,允许工程师将塔式起重机打开到以下水平并跳进以避免冲突并按时完成钢结构的构建。

4D模型提供对结构的可视性(图像来源:ALEC Engineering)

世界上最大的悬臂可以在塔A和塔之间建立;截至2019年10月22日的情况(图片来源:ALEC ENGINEERING)

提前上述冲突的可见性有助于该项目节省至少1200万美元。特别是使用4D模型以及助理图像,帮助提供利益相关者对不可预见的风险及时了解,并提高项目的性能。它还减少了手动工作,提高了促进过程中的通信效率和改进的决策。该项目仍在建设中,直到2019年,4D造型导致期初延迟发生冲突检测和更好的规划期限减少了70天。此外,该项目目前迄今为止,通过清楚地了解计划,精确可视化和结构的可见性和改进的沟通,节省了1600万美元。